Granular A and B, tonnes vs cubic metres, swell and shrink, compaction lifts, trenches and pipe bedding — in plain language, with the tools to go with them.
The two granulars you'll order most are A and B — and they're not the same thing.
Think of it as a stack: Granular B does the heavy lifting down deep, Granular A provides the smooth, dense platform the pavement sits on. On asphalt work you'll see this exact stack under the lifts — see the asphalt field guide for the full cross-section.
The same material has three different volumes depending on where it is.
Digging loosens material and it takes up more space in the truck (swell); compacting it back squeezes it into less space than the original hole (shrink). Swell and shrink vary by material — rock swells more than clay, and some materials barely shrink at all. Use the project's assumed factors when you can; otherwise treat 20–30% swell and 10–15% shrink as starting points, not guarantees.
A common working density for granular base is around 2.0–2.2 t/m³ compacted (lighter loose). Check the material's actual density — it changes the truck count.
Fill is placed in thin lifts and compacted to a spec'd percentage — never dumped deep and rolled.
Compaction % is field density ÷ maximum (Proctor) density × 100. Fill is placed in lifts (commonly 150–300 mm loose per lift, depending on the material and equipment) and each lift is compacted before the next goes on. The spec sets the required % (95–98% is typical for structural fill) and the test method.
A trench isn't just a hole — it's bedding, pipe zone, backfill and cover.
The bedding under the pipe is shaped and compacted so the pipe sits evenly (never on hard spots). The pipe zone around the pipe is usually granular or sand, placed carefully so the pipe isn't damaged. Above that, backfill goes in compacted lifts. Excavation also needs to be sloped or benched (or shored) to keep it safe — never work in an unsupported trench.
The stuff you learn watching the dozers.
Calculate the volumes, plan the haul, and carry it all into the earthwork workflow and daily report.