Calculators › Tack / Prime Coat

Tack Coat & Prime Coat Calculator

Estimate emulsion volume for tack and prime coats before your next paving job.

Inputs

Typical rates: tack 0.2–0.5 L/m², prime 0.5–1.0 L/m². Confirm with your spec.
Tip: use the Asphalt Tonnage calculator to get your paving area.
Allows for wind drift, overlaps, and cleanup.

For estimation purposes only. Terms of Use

Result

litres of emulsion
Area
Rate
US gallons
Imp gallons

How to Calculate Tack Coat

  1. Get the paving area in square metres (length × width of the surface being overlaid).
  2. Choose your application rate: tack coat is usually 0.2–0.5 L/m²; prime coat 0.5–1.0 L/m² — follow the project spec.
  3. Multiply area × rate, then add spray loss: multiply by 1 + waste% and compare with your distributor's tank capacity.

Formula Used

Emulsion (L) = Area × Application rate × (1 + Waste %)

Worked Example

A 2,000 m² resurfacing job at 0.35 L/m² with 5% spray loss:

Emulsion = 2000 × 0.35 × 1.05 = 735 litres
≈ 194 US gallons ≈ 162 Imp gallons

When to Use This Calculator

Use this when ordering emulsion for tack coats before hot-mix overlays, or prime coats on granular base — so the distributor delivers the right volume and you don't run short mid-job.

When Not to Use This Calculator

Actual rates are set by the owner's specification or mix design. This is an estimating tool — always confirm the specified rate before ordering.

Frequently Asked Questions

What's the difference between tack and prime coat?

Tack coat bonds a new asphalt layer to an existing asphalt surface. Prime coat is applied to granular base before paving to bind and seal the surface.

How much tack coat do I need per square metre?

Typically 0.2–0.5 L/m² depending on the surface condition — rougher or more oxidized surfaces take more. Use the spec rate when one is provided.